Cars are parked on Main Street Tuesday morning, Sept. 6, signifying the progress that has been made on the city of Freeman's $5.1 million capital project. The downtown roadway is open to traffic from Fifth to Third streets, with concrete work finishing up on the one block of roadway from Third Street north to Railway. Attention will then turn to the pouring of concrete from Railway north to the North County Road, as well as the reconstruction of the side streets.
September 6, 2022
Cars are parked on Main Street Tuesday morning, Sept. 6, signifying the progress that has been made on the city of Freeman's $5.1 million capital project. The downtown roadway is open to traffic from Fifth to Third streets, with concrete work finishing up on the one block of roadway from Third Stree...